Free Loop check sheet Excel template
By a practising automation / electrical engineer with more than ten years · Updated 2026-11-22
As-found / as-left rows for commissioning. Not a FAT certificate.
Sheet: Loop Check. Includes an Instructions tab and example rows.
Download XLSXColumns
| Column | Required | Note |
|---|---|---|
| Loop Tag | Yes | Instrument tag |
| Signal | No | AI, AO, DI, DO |
| As Found | No | Site reading or state |
| As Left | No | After adjustment |
| Date | No | Check date |
| Tech | No | Technician |
| Notes | No | Free text |
Example rows
| Loop Tag | Signal | As Found | As Left | Date | Tech | Notes |
|---|---|---|---|---|---|---|
| PT-1001 | AI | — | — | — | — | — |
| FT-2001 | AI | — | — | — | — | — |
Commissioning loop checks
A loop check is the field verification that a loop reads and responds as designed. The sheet records the tag, the signal, the as-found value, the as-left value after adjustment, the date, and the technician.
It is a working record for the commissioning team, not a signed factory acceptance test. SchematicForge issues no certificate.
As-found vs as-left
As Found is the reading before anyone touches the loop. As Left is the reading once the loop is calibrated. The gap between them is the evidence that work happened, which is why both columns are kept.
For a digital signal the value is a state, such as open or closed, rather than a number.
Where it sits in the package
The check sheet is the last mile of the loop folder: after the diagrams, register, and schedules are issued, the checks are filled in on site against the issued tag numbers.
Importing this workbook works like a vendor IO list — upload it in the IO list checker or on the home page, review the mapping, and create loops.