Free FAT checklist Excel template

By a practising automation / electrical engineer with more than ten years · Updated 2026-11-22

Factory acceptance checklist: loop tag, check, expected, as-found, pass/fail. Not a signed FAT certificate.

Sheet: FAT Checklist. Includes an Instructions tab and example rows.

Download XLSX

Columns

ColumnRequiredNote
ItemYesRow number
Loop TagYesInstrument tag
CheckYesWhat is verified on the bench
ExpectedNoExpected reading or state
As FoundNoBench reading — leave blank until the test
Pass/FailNoFilled on the bench
DateNoTest date
TechNoTechnician
NotesNoFree text

Example rows

ItemLoop TagCheckExpectedAs FoundPass/FailDateTech
1PT-1001Analog 4 mA live zero0 barg————
2PT-1001Analog 12 mA mid-span5 barg————
3ZS-2001Open-limit contactBOOL 1 when open————

First eight columns shown. Download the XLSX for the full sheet.

What a FAT checklist is for

A factory acceptance test checklist is the bench record that a loop, cabinet, or package behaves as specified before it ships. Rows are checks, not live plant readings: analog live zero, mid-span, a limit contact, a trip output.

This workbook is a blank with three example rows. It is not a signed FAT certificate, not a SIL document, and not generated from a controller configuration.

FAT versus loop check versus SAT

FAT is on the vendor floor. A loop check is as-found / as-left on site against the issued tag. SAT is site acceptance of the installed system. SchematicForge already issues a loop-check sheet template and, on paid packs, SAT sheets from the IO list. This FAT file stays ungated and blank.

Do not treat a filled row as a certificate. An engineer still signs the project FAT procedure.

Where it sits in the package

Use it next to the loop-check sheet and the cause-and-effect matrix. Upload an IO list when you want drawings, the Loop Register, and schedules from the same tags.

Importing this workbook works like a vendor IO list — upload it in the IO list checker or on the home page, review the mapping, and create loops.