Factory acceptance checklist: loop tag, check, expected, as-found, pass/fail. Not a signed FAT certificate.
Sheet: FAT Checklist. Includes an Instructions tab and example rows.
Download XLSXColumns
| Column | Required | Note |
|---|---|---|
| Item | Yes | Row number |
| Loop Tag | Yes | Instrument tag |
| Check | Yes | What is verified on the bench |
| Expected | No | Expected reading or state |
| As Found | No | Bench reading — leave blank until the test |
| Pass/Fail | No | Filled on the bench |
| Date | No | Test date |
| Tech | No | Technician |
| Notes | No | Free text |
Example rows
| Item | Loop Tag | Check | Expected | As Found | Pass/Fail | Date | Tech |
|---|---|---|---|---|---|---|---|
| 1 | PT-1001 | Analog 4 mA live zero | 0 barg | — | — | — | — |
| 2 | PT-1001 | Analog 12 mA mid-span | 5 barg | — | — | — | — |
| 3 | ZS-2001 | Open-limit contact | BOOL 1 when open | — | — | — | — |
First eight columns shown. Download the XLSX for the full sheet.
What a FAT checklist is for
A factory acceptance test checklist is the bench record that a loop, cabinet, or package behaves as specified before it ships. Rows are checks, not live plant readings: analog live zero, mid-span, a limit contact, a trip output.
This workbook is a blank with three example rows. It is not a signed FAT certificate, not a SIL document, and not generated from a controller configuration.
FAT versus loop check versus SAT
FAT is on the vendor floor. A loop check is as-found / as-left on site against the issued tag. SAT is site acceptance of the installed system. SchematicForge already issues a loop-check sheet template and, on paid packs, SAT sheets from the IO list. This FAT file stays ungated and blank.
Do not treat a filled row as a certificate. An engineer still signs the project FAT procedure.
Where it sits in the package
Use it next to the loop-check sheet and the cause-and-effect matrix. Upload an IO list when you want drawings, the Loop Register, and schedules from the same tags.
Importing this workbook works like a vendor IO list — upload it in the IO list checker or on the home page, review the mapping, and create loops.